Solian Investment Limited v Ksc International Limited In Receivership (formerly Known As Kundan Singh Construction) & 6 others
The bottom line
#The Court of Appeal refused Solian Investment more time to file its appeal, ruling the company failed to diligently track its own case progress.
What this practically means
#Executive summary
#Key legal issues
#Extension of time under Rule 4 of the Court of Appeal Rules
Extension of time is an equitable remedy, not a right; the applicant bears the burden of explaining the delay to the court's satisfaction.
The court applied the well-established Rule 4 factors: length of and reason for delay, chances of the appeal succeeding, prejudice to the respondent, effect on public administration, and importance of compliance with time limits. Citing Salat v IEBC, it held that the applicant must lay a basis to the court's satisfaction, that each case is considered on its own facts, and that public interest is relevant.
Whether the delay was excusably explained
No: the applicant knew by 30th January 2023 that proceedings had been requested, and due diligence would have revealed they had been collected in December 2022.
The new advocates applied afresh for proceedings on 14th March 2024 without perusing the court file or enquiring of the former advocates. Even after learning on 21st August 2024 and collecting proceedings on 3rd September 2024, the application was filed on 13th December 2024 without adequate explanation; unavailability of pleadings did not prevent earlier filing, as prior applications showed.
Mistake of counsel as a ground for extension
Mistake of counsel is not an automatic excuse for delay.
Relying on Sakari v Anyumba, the court held that a case belongs to the litigant, not counsel, so counsel's inaction cannot by itself justify extension. The applicant's analogy to authorities holding that mistakes of former counsel should not be visited on a client did not avail it, given the absence of due diligence over an extended period.
Prejudice to the respondent
Further delay would prejudice the 1st respondent, which is in receivership, in a suit commenced in 2016.
The court noted the suit's age since 2016 and the 1st respondent's receivership, accepting that prolonged delay in concluding the matter was prejudicial. This factor weighed against extension alongside the unexplained delay and the importance of compliance with time limits.
Legal principles established
#- Mistake of counsel is not an automatic reason to excuse delay, as the case belongs to the litigant and not to counsel
- Although the Rule 4 discretion is unfettered, it must be exercised judicially on established relevant factors
- A litigant whose advocates have requested proceedings must exercise diligence, by perusing the court file or enquiring of former advocates, to establish the status of the request
Court orders
#- 1.The application dated 13th December 2024 is dismissed
- 2.Costs of the application awarded to the 1st respondent
- On appeal from
- Environment and Land Court
- ELC Case No. 22 of 2016
- Jurisdiction invoked
- Rule 4 of the Court of Appeal Rules (extension of time discretion)
Key timeline
#Practical implications
#Frequently asked questions
#Cite this brief
#Cite this brief
Caselaw, "Solian Investment Limited v Ksc International Limited In Receivership (formerly Known As Kundan Singh Construction) & 6 others", Case Analysis (2025). Civil Application (Malindi) arising from ELC Case No. 22 of 2016; related Civil Application No. E001 of 2023 and E010 of 2024. Source: https://new.kenyalaw.org/akn/ke/judgment/keca/2025/1533/eng@2025-10-03
Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.