AI-generated case brief
Case Brief · caselaw.co.ke
ELCPartially AllowedELCC No. 28 of 2022

Watamu Hospital Limited v ATC Kenya Operations Limited & National Environment Management Authority (Interested Party)

Environment and Land Court of Kenya
30 September 2026
11,837 words in judgment
View original judgmentRead on Kenya Law Watch case
AI-assisted case brief
·~47 min to read original · ~4 min brief

The bottom line

#

A Kenyan court ordered a telecom company to remove a phone mast built near Watamu Hospital because it started construction before getting proper environmental approval.

What this practically means

#

Executive summary

#
Watamu Hospital Limited sued ATC Kenya Operations Limited over a Base Transceiver Station erected about 20 metres from its medical facility on parcel Gede/Kirepwe/B80, alleging construction began without approvals from the National Construction Authority and NEMA and without the environmental impact assessment and public participation required by EMCA and the Environmental (Impact Assessment and Audit) Regulations. The plaintiff sought declarations, mandatory injunctions to demolish the mast, general damages and costs. The defendant maintained it obtained all licences and approvals and that public participation was supervised by NEMA. NEMA, the interested party, did not participate in the hearing. The court framed five issues. On the evidence, construction had commenced before the suit was filed in April 2022; NCA issued a Suspension of Works Order on 21st April 2022; the questionnaire relied on by the defendant was completed on 30th April 2022; and the EIA Licence was only issued on 16th November 2022. DW1 admitted these dates. The court held that telecommunications infrastructure falls within the Second Schedule to EMCA and required a full EIA Study Report, not the Comprehensive Project Report produced, and that no evidence showed NEMA dispensed with the study under the proviso to Section 58(2). The questionnaire exercise did not amount to the meaningful public participation required by Regulation 17. The court found the EIA Licence was obtained unprocedurally, revoked it, held that the later licence could not retrospectively cure the illegality, and found a violation of Article 42. Applying the Supreme Court's CMM decision, it awarded Kshs. 200,000/= in general damages without requiring proof of physical injury, granted prayers (a), (c), (d) and (f), ordered removal of the BTS within 60 days under NEMA and County Government of Kilifi supervision, with removal costs and the costs of the suit borne by the defendant.

Questions the Court framed

#

The issues the Court set itself to decide, in its own words.

  1. 1.Whether the Base Receiver Transmission Station was constructed after compliance with the procedural requirements under the EMCA Act
  2. 2.Whether the construction of the Base Transmission Station is harmful to the Plaintiff's right to a clean and healthy environment, and if so, what reliefs the Plaintiff is entitled to
  3. 3.Whether the Licenses issued to the Defendant ought to be cancelled by an order of this court
  4. 4.Whether the Base Transmission Station ought to be demolished
  5. 5.Whether the Plaintiff is entitled to general damages for violation of the right to a clean and healthy environment

Key legal issues

#
01

Compliance with EMCA procedural requirements before construction

Holding

The BTS was commenced without compliance with the mandatory procedural requirements under EMCA and the Regulations; the later EIA Licence did not cure the illegality

Reasoning

Construction had commenced before the suit was filed in April 2022; NCA issued a Suspension of Works Order on 21st April 2022; the questionnaire relied on was signed 30th April 2022; the EIA Licence was only issued on 16th November 2022. DW1 admitted the licence date and that the mast was incomplete on 30th April 2022. The chronology showed implementation preceded the environmental process.

p. 23
02

Whether an EIA Study Report or a Comprehensive Project Report was required

Holding

A full EIA Study Report was required because telecommunications infrastructure falls within the Second Schedule; the Defendant failed to show NEMA exercised the Section 58(2) proviso

Reasoning

The Second Schedule expressly lists telecommunication infrastructures. Section 58(2) requires a full study report unless the Authority directs otherwise. The Defendant produced only an EIA Comprehensive Project Report and adduced no evidence that NEMA dispensed with the study report, so the assessment process was incomplete at commencement.

p. 24
03

Whether public participation was adequate

Holding

The questionnaire exercise did not constitute the full and meaningful public participation required by Regulation 17; engagement occurred after implementation had commenced

Reasoning

PW1, PW2 and PW3 all received questionnaires after construction had begun or completed. DW1 was unsure whether a sensitization forum was held and had no minutes. A questionnaire completed on 30th April 2022, after construction commenced and after suit was filed, could not show the community had a reasonable opportunity to influence the assessment before implementation.

p. 31
04

Whether the EIA Licence should be cancelled

Holding

The EIA Licence was obtained unprocedurally and was revoked

Reasoning

The licence was issued long after commencement of construction and after the suit was instituted. The Defendant did not show a full EIA Study Report was submitted and considered under Section 58(2), nor that Regulation 17 public participation preceded commencement. The issue was not NEMA's jurisdiction but the legality of the process preceding the licence.

p. 41
05

Whether the BTS ought to be demolished/removed

Holding

A mandatory removal order was granted as a remedial, not punitive, measure

Reasoning

The BTS was commenced in disregard of statutory environmental safeguards, in proximity to a hospital, without prior EIA Study compliance or meaningful participation. Allowing it to remain would permit continuance of an unlawfully established development and reward non-compliance with environmental law.

p. 46
06

General damages for violation of the right to a clean and healthy environment

Holding

Kshs. 200,000/= awarded as constitutional compensation despite absence of expert medical evidence of injury

Reasoning

The claim is founded on Article 42 and is constitutional, not tortious. Following CMM v Standard Group, once a violation is proved on a balance of probabilities, proof of actual loss is unnecessary. The court considered the nature and duration of the violation, deliberate pre-licensing commencement, proximity to the hospital, generator noise and failed public participation.

p. 54

Legal principles established

#
  • A proponent may not commence implementation of a Second Schedule project and later regularize it by obtaining an EIA Licence; assessment and licensing must precede commencement
  • Projects in the Second Schedule to EMCA require a full EIA Study Report, not a mere project report, unless NEMA lawfully directs otherwise under the proviso to Section 58(2)
  • A subsequent EIA Licence cannot retrospectively cure the procedural defects of a project commenced before licensing
  • Once a violation of a constitutional right is proved on a balance of probabilities, proof of actual loss or damage is not a prerequisite to compensatory relief

Court orders

#
  1. 1.Declaration that the EIA Licence issued to the Defendant for the Watamu Base Transceiver Station on Land Parcel No. Gede/Kirepwe/B/80 was obtained unprocedurally, is unlawful, and is revoked
  2. 2.Grant of prayers (a), (c), (d) and (f) as prayed in the plaint dated 26th April 2022
  3. 3.Mandatory order that the Defendant remove the telecommunication tower (base transceiver station) built on Gede/Kirepwe/B80, originally Gede/Kirepwe/B216, within sixty (60) days of the judgment
  4. 4.In default of compliance, the Plaintiff may procure a qualified contractor to enter the parcel, remove the tower and associated structures and cart away the debris
  5. 5.Removal to be supervised by NEMA and the County Government of Kilifi
  6. 6.Costs of the demolition and removal to be borne by the Defendant
  7. 7.General damages of Kshs. 200,000/= for violation of the right to a clean and healthy environment
  8. 8.Defendant to bear the costs of the suit

The bench

#

One judgment of the whole court — no separate or dissenting opinions.

majority

Wrote the judgment

Jurisdiction invoked
Original jurisdiction of the Environment and Land Court over environmental and land use disputes (Article 162(2)(b) Constitution); claim founded on Article 42 and Section 58 EMCA

Relief refused

#

Prayer (b) of the plaint (mandatory injunction with self-help demolition within 7 days) - not granted as such; instead a supplemental 60-day removal order under prayer (c) was issued

The court granted prayer (c) with a 60-day period and supervised removal rather than the 7-day self-help demolition in prayer (b)

Costs

The Defendant shall bear the costs of the suit.

Quotable passages

#

Verbatim from the judgment, each located to the page it appears on in the official PDF — so these can be cited and checked directly.

The law does not contemplate that a proponent may commence implementation and subsequently regularize the project through the issuance of an EIA Licence.
p. 22No retrospective regularization of unlicensed projects
the Court finds that the EIA Licence issued to the Defendant was obtained unprocedurally and cannot lawfully sustain the development.
p. 41Unprocedural EIA licence
the questionnaire exercise relied upon by the Defendant did not, on the evidence adduced, constitute the full and meaningful public participation contemplated by Regulation 17.
p. 31Public participation under Regulation 17
This court further grants prayers no (a), (c), (d) and (f) as prayed in the plaint dated 26th April 2022.
Final orders - prayers granted
the Defendant shall remove the telecommunication tower (base transceiver station) built on the parcel of land known as Gede/Kirepwe/B80, originally Gede/Kirepwe/B216, within sixty (60) days of this judgment
p. 55Final orders - mandatory removal within 60 days
The Defendant shall also bear the costs of the suit.
p. 55Final orders - costs

Issues in the judgment

#
minor

Paragraph numbering is disordered - numbers 26, 28, 29 and 76 are each used twice, and sequence jumps from 57 to 62 and 66 to 67

minor

Defendant's defence dated '29th February 2024' - 2024 was a leap year so date is valid, but plaint amendment dated '26th February 2024' vs filing header 'FABM-31.01.24' differ

minor

Revocation clause uses mixed number agreement: 'was obtained unprocedurally, and are thus unlawful and is hereby revoked'

Key timeline

#

Practical implications

#

Frequently asked questions

#

Cite this brief

#

Cite this brief

Caselaw, "Watamu Hospital Limited v ATC Kenya Operations Limited & National Environment Management Authority (Interested Party)", Case Analysis (2026). ELCC No. 28 of 2022. Source: https://new.kenyalaw.org/akn/ke/judgment/keelc/2026/6125/eng@2026-09-30

Suggested citation format for research notes or client memos. Always verify the original judgment before relying on any point.